Back to Current ProjectsNorfolk Southern Intermodel FacilityDrawings Admin Building Crew and Maintenance Building S001 Specs Administration-building-specifications Crew-and-Maintenance-Building-specifications Norfolk Southern 2010 Contractor Guidelines (2) NSR Standard Specifications - 2011 January (2) PennDot Prevailing Wage Guidelines PennDot Standard Contract Provisions (2) PennDot US Steel Products Requirements (2) photo_10 5 107 50_enkdh 20110609T022820 Proposal Form 3 Buildings Constructed for Franki Request For Quotation 3 Buildings Constructed fo Sample Contract 3 Building Construction Franklinpdf State Prevailing Wage Rates for Franklin County% PA-A-12 48 13[1] - ENTRANCE FLOOR MATS AND FRAMES E 1 Admin Bldg Lighting & Power E 2 ADMIN Electrical Schedules
Please note responses to questions below.1) The finish schedule for the maintenance building calls for ceramic tile base and wall tile to 6’4” AFF but interior elevations on A501 shows painted CMU and vinyl base. Which is correct? a. The walls are to receive ceramic wall tile to 6’4” AFF and ceramic base as described in the finish schedule. 2) Please provide specification for the recessed walk-off mat. a. See attached specification section. 3) Please provide specification for the tack and marker boards. a. Specifications will be provided next week. 4) Please provide specification for the polished concrete system. a. Specifications will be provided next week. 5) Please provide specification for the fire alarm system. Is the designer of the fire protection systems required to determine what the requirement is for the fire alarm systems or are you providing that information? a. The designer of the fire protection systems is responsible for determining fire alarm system requirements. 6) The crew and maintenance building specifications calls for sprinkler system only in the Hostler Maintenance Area. The plumbing drawings are only showing 2” CW service for these buildings and only a 3/4” line for the maintenance building. #1 Are these buildings to be protected by automatic sprinklers and if so, please provide size and location of the underground service. #2 Please indicate the areas for the Administration Building that are to receive the FM-200 systems. a. The Hostler Repair area (room 301 on sheet A-201 of the Maintenance & Crew Building plans) is to include an automatic sprinkler system. A 6” DI fire service will be provided 5’ outside the building, near the northwest corner of the building. b. The AGS Server room (room 102 on sheet A-201 of the Administration Building plans) is the only area to be protected by the FM-200 system.
1. Still researching window solution. 2. No. Sunshades per specification (or approved equals) 3. No bid bond. 1) The operable awning panels shown on the plans are not available in Kawneer 8400TL series. Sliding, single, and double hung are the options with 8400TL. Please clarify. 2) If the sunshades are required to be Vistawall as previously mentioned in an RFI then you eliminate the other (15) manufactures that are specified for the curtain wall system. Is that what you intend No. Sunshades 1) The Tile specifications for the Crew and Maintenance buildings only notes paver tile. Please provide specifications for wall tile and base. Will there be pattern or any accent colors? Are the wall areas required to be waterproofed? a. Please see the attached revised specification which includes wall tile and base. This specification shall replace section 09 30 00 for the Crew & Maintenance Buildings only. There will be no patterns or accent colors. The wall areas within 3’ of plumbing fixtures are to be waterproofed. The remaining walls do not require waterproofing. 2) The plans for the Crew and Maintenance shows plastic laminate cabinetry but the specifications call for wood veneer. Which is correct? a. All cabinetry is to be wood veneer. 3) The Mechanical Equipment Schedule on drawing E-3 of the Administration building indicates the HPU’s being fed from Panel PA2. This panel is missing from the riser diagram nor is there a Panel Schedule for this panel. What size is Panel PA2? What is it fed from and feeder size? Location? Does the size of Transformer T1 need to change? a. Panel PA2 was inadvertently omitted from the plans. Revised plans are being prepared and will be distributed showing the details of this panel. 4) During the pre-bid meeting sidewalks and pads were mentioned as part of the project. The structural drawings show one turn down pad at exterior door 12 of the Administration building. Additionally note is a pad for the bicycle rack. No other pads or sidewalks are noted for any of the buildings. Please clarify the concrete scope of work at the exterior of all the buildings. a. The scope of work for concrete outside the building is limited to what is shown on the plans and specifications (e.g. HVAC equipment pads) . Any additional exterior concrete will be provided by others. Below are a handful more RFI’s 1. Will the site contractor need to cut or fill to achieve the desired grade at building pads? No. 2. For building footer purposes is this a classified or unclassified site? Unclassified. 3. Can excavated soils be disposed of on site? Yes, we will find an area on site to dispose of excavated soils. 4. Can excavated soils be used as backfill? Yes, if it meets spec. 5. Reference Spec Section 084413, part 2.3 “sunshades”. Will the other approved manufactures’ standard sunshade configuration be acceptable as long as they are similar in appearance? No. 6. Reference Spec Section 088000, part 1.3, paragraph designates engineer analysis. As this is a singles story building not subject to high windloads and the specified glass is a fairly typical product, will engineer review be required? Yes. 7. The window schedule on sheet A-811 designates a Kawneer 6200T. Kawneer has discontinued manufacturing on the product. Can we assume that another window with the same performance characteristics will be accepted? No. Change to Kawneer 8400TL series. 8. Spec Section 084113 part 2.5 designates a 2” thick doors. Industry standard is 1-3/4”, please clarify 1 ¾” is also acceptable. 9. Spec Sections 084113 & 084413 designate LEED requirements for sealants but does not ask for recycled content, please clarify. Recycled content shall be considered for LEED for sealants.
Answers to RFI:July 07, 2011 July 07, 2011 1) The operable awning panels shown on the plans are not available in Kawneer 8400TL series. Sliding, single, and double hung are the options with 8400TL. Please clarify. 1. Still researching window solution. 2) If the sunshades are required to be Vistawall as previously mentioned in an RFI then you eliminate the other (15) manufactures that are specified for the curtain wall system. Is that what you intendNo. Sunshades No. Sunshades per specification (or approved equals) 3) Is a bid bond required and if so what percent? 3. No bid bond July 07, 2011 Refer to question #5; if the Vistawall sunshade is the only approved product you have eliminated the other manufacturers listed in the specification. Other approved manufactures listed in spec. are approved products. Refer to question #7; The Kawneer 8400TL is not a projected window as shown on the elevations. Use the Kawneer 8225TL Isolock window. July 07, 2011 Leed Requirements 1. Who is responsible to make to submission to USGBC for the project? Contractor with assistance of owner/architect 2. Who will pay the USGBC Submission Fees? Owner 3. For Credit EA 5 will the CxA pay the cost of Measurement and Verification? Contractor to pay this fee. 4. For Credit IEQ 7.2 Verification, who is responsible to do this? Contractor. Payment 5. When will retainage be released? After final payment for date of substantial completion. (The Commissioning EA 3 and the Measurement and Verification EA 5 is to be 12 months and the Thermal Comfort IEQ 7.2 Verification is to be 18 months. the LEED Certification will not be finaled until after that.) 6. Will the retainage be held during this period? We will release retainage for work completed up to date of substantial completion. 7. If so will the retainage for the Crew and the Maintenance be held also? Retainage will be held and released after date of substantial completion. General 8. Will the buildings be in a cut or fill area of the overall site? Both fill and cut. 9. If a cut is there any borings report for the building sites? No. 10. The drawings for both buildings call for the slab to be "placed on compacted subgrade" sheet S-001 note 2.05. Sheet S-002 shows stone in details, but no notes. all other locations reference back to 2.05. Is stone under slab required and how thick? Yes, 4” #57. 11. I have received 5 RFI responses (3 Rockwell & 2 B&H) is this the correct number? Yes. July 08, 2011 July 08, 2011 1. What Size is Panel PA2? 225A. See attached revised drawing sheets. 2. What is PA2 fed from and the feeder size? Sub-feed of panel PA. See attached revised drawing sheets. 3. Where is PA2 located? Mechanical Rm.109. See attached revised drawing sheets. 4. Does the size of Transformer T1 need to change? No 5. Can we get some clarification regarding surge protection? There are three different exposure levels High; Medium and Low for each of service entrance; distribution and branch panels. Refer to surge protection specification 26-43-1. This facility will be considered Medium Exposure. 6. Is a specification for transformers available? Attached please find transformer specification 26-12-16 (the same as distributed earlier today under separate cover). 7. There is a note in Panel board specification 26 24 162.1 Q “ All panel boards fed from UPS systems and K-rated transformers shall be furnished with 200% rated neutral bus bars and separate insulated/isolated ground Bar” I have concern regarding panel board PA of administration building as there is mention of AGS Server receptacles. Provide isolated ground bar for panel PA. 8. There are no meter bases or ct cabinets shown on drawings post the utility transformers. Is the utility metering at their transformers? The entire facility shares a single meter that is being installed under a separate contract. Revised sheet E-3 (attached) adds a meter after the transformer for the administration building. This meter is only for measurement and verification of LEED credit EA5 as described in section 01 81 13.13 of the specifications. 9. Drawings show lighting contactors LC off panel boards PMA and PA. How many poles are needed? 3-poles 10. Are there specifications for lighting contactors? Refer to attached drawing E-3. July 08, 2011 July 08, 2011 Is there a sign schedule or sign detail for the room signage? No, only the drawings and specifications. Logo design will be furnished by owner to successful bidder for sign manufacturing. Please provide the specifications for the concrete polish system and marker boards mentioned below. Specification sections 10 11 00 for visual display surfaced and 03 35 23 for polished concrete finishing are attached.
|
||